Premier Project Profile

Salta Estate: Infrastructure Package

This premier infrastructure development project at the Salta multi-purpose development in Umdloti is being undertaken for DEVMCO by Stefanutti Stocks Coastal. The contract runs between May 2021 and September 2022.

Background: This extremely fast track mixed used development project is located approximately nine-kilometre northeast of Umhlanga, directly adjacent to the small town of Umdloti in KwaZulu-Natal. Of the 170-ha site, approximately 115,3-ha is being developed. The completed SALTA estate will comprise free hold residential homes, sectional units, retirement village, a retail centre, as well as a commercial office development.

The Project Scope

Stefanutti Stocks Coastal is constructing the following infrastructure required for this development to be built:

  • Bulk earthworks, including for buildings/structure platforms,
  • Bulk sewer infrastructure and internal sewer house/unit connections,
  • Bulk storm water pipeline, inlets, and manholes,
  • Various types of roads (access roads, internal roads, lower ring road, entrance road),
  • Stormwater infrastructure, including culverts and numerous attenuation structures,
  • Electrical reticulation,
  • Water reticulation,
  • Service sleeves for data and fibre cables, and
  • Reinforced concrete and dry stack retaining walls.

Both the client and professional team are very target driven. The project is a phased development with access for the top structure contractors (which are direct to the client) for the retail and sectional title units required by the end of 2021, followed by the free hold, commercial and retirement village in the first quarter of 2022.

The construction of primary, secondary, and tertiary roads entails the bulk earthworks, numerous and complex service installations, the construction of the engineered layers, and finally the asphalt wearing course. The entire estate is to be completed by end of August 2022.

 

Expected Quantities (approximate)

  • 450 000 cut to fill
  • 13km sewer pipelines
  • 10km storm water
  • 20km of primary, secondary, and tertiary roads
  • 40km of kerb/channel