Client: Sasol
Description: Installation of mechanical equipment; electrical and instrumentation; fabrication and installation of piping spools and process systems.
- Mechanical equipment: 700 tons
- Structural steel: 400 tons
- Pre-assembled modules and racks: 734 tons
- Process piping-welding of 110 000 diameter inches for fabricated spools and 12 000 diameter inches for erection.
- Electrical & instrumentation
- Rack: 3 500 metres
- Conduit: 15 500 metres
- Cable: 187 000 metres
- Junction boxes: 1 486
- Instruments: 1 036
- Earthing: 6 300 metres
- Tubing: 9000 metres
Division: Stefanutti Stocks Oil & Gas